Bridge construction process

Bridge construction process

January 4, 2026

1. Material preparation


2. Bridge treatment requirements

(1) The bridge deck should be free of floating slurry and debris,Water-repellent bonding layer+Before construction, it should be selected according to the actual situation of the bridge deckSandblasting+、Fine millin+ The cement concrete bridge deck is treated in a way to remove floating slurry and debris, and remove the excessive protrusion.

(2) The bridge deck should be dry and clean, and if the bridge deck should be rinsed with water after treatment to ensure that the surface is clean, there should be no visible dust, oil and other secondary pollution. Ensure that the cement concrete bridge deck is dry and clean before the construction of the waterproof bonding layer.

(3) Before the construction of the waterproof bonding layer of the bridge deck, the treatment quality of the bridge deck should be checked, and the inspection items and standards are listed in the table below.


Inspect the itemunitInterface requirementsNote with the inspection method and frequency
flatnessmmThere is no obvious protrusion or depression, and the maximum clearance of the three-meter ruler is not greater than 5, and the elevation deviation is not greater than 153 sections/100m
appearance/The surface should be firm, strong, without floating slurry, there should be no obvious dust to the touch, and there should be no sharp protrusions such as steel bars and aggregatesRandom detection
Construction depthmmThe measured structural depth of the sand laying method is not less than 0.303 sections/100m
Dryness%No watermarks or water marks on the surface3 sections/100m

Table 5.1-1 Requirements for cement concrete bridge deck interfaces


3. Cleaning of the base layer of the bridge deck beam

(1) Use shot peening equipment to blast and brush the bridge deck

(2) For the surface of the concrete bridge deck foundation, first manually clean a large amount of gravel and sand, manually clean up the loose debris, and use slag cleaners, milling machines and other mechanical equipment to treat the bridge deck, requiring no floating slurry, flat, clean, no clear water, and clean surface.


4. Preparation of construction machinery

(1) A spraying machine should be used to spray the waterproof coating of roads and bridges over a large area, and spray at room temperature. If the construction area is small, manual painting can also be used.

(2) Before construction, the spraying machine and spraying pipe should be thoroughly cleaned, and the material should be completely cleaned before loading, and no residue of the previous batch of materials is allowed.

(3) Inspect each nozzle before construction, and each nozzle does not have any blockage to ensure that the construction process is carried out normally. The sprayer is strictly prohibited from heating with fire and spraying at room temperature.

(4) The spraying machine should be rinsed immediately after spraying.


5. Waterproof adhesive layer spraying

(1) After the water washed by the bridge deck is dried, the special waterproof coating for roads and bridges can be sprayed with a spraying machine.

(2) It should be sprayed in layers, and it should be completed 3~4 times. The latter pass should be cured into a film in the direction of the previous pass and perpendicular to the previous pass.

(3) The construction temperature should be 5°C~35°C. The temperature is less than 5 °C and rainy days (including rain within 6 hours after construction) are not allowed to be constructed.


6. Waterproof layer maintenance

(1) During the construction process, it is strictly forbidden to step on the undried work surface, and strictly prevent nails, wooden sticks, steel bars and other sharp objects from artificially damaging the work surface.

(2) After the waterproof layer is dry, it should be carried out as soon as possibleAsphalt mixtur+Paving. Before paving asphalt, the method of spreading fine-grained asphalt mixture on the surface of the waterproof layer can be used to make an isolation layer to prevent damage to the coating film